Within the management plans of the Arabian Gulf Oil Company, and the recommendations of the National Oil Corporation to raise production, on 08/11/2022 the operation of the well G318 at Terminal 5 was completed and put on production after great and continuous efforts to complete all the mechanical connection work and all electrical works on the well G-318, as well as the placement of columns, the installation of insulators and arms, the tightening of wires to the final stage and the connection of the electrical transformer To feed the ESP pump where the field controller reported that this well is the third of a total of 6 wells being carried out and works on wells G-242, G-292 and G-319 are still under completion and in their final stages.